A civil and environmental engineering team designs an optimal utility pipeline trajectory connecting a wastewater treatment plant across a 600-m wide wetland corridor to a discharge terminal 2000 m downstream. Wetland directional drilling costs $400/m while dry utility easement trenching costs $240/m. We formulate the cost objective, establish the physical domain, find the optimal crossing point using the Closed Interval Method, and demonstrate Snell's Law equivalence.
Step-by-Step Mathematical Solution
Step 1: Formulate the Total Construction Cost Objective Function
The total project capital expenditure is the sum of the wetland installation cost and the dry overland easement installation cost:
Wetland Segment:
The pipeline originates at (0,600) and drills diagonally under the wetland to point P(x,0) on the southern easement bank. By the Pythagorean Theorem:
dwetland(x)=6002+x2=360,000+x2 meters
Cost: Cwetland(x)=400360,000+x2 dollars.
Dry Easement Segment:
From P(x,0), the pipe runs along the dry riverbank to terminal T(2000,0):
dland(x)=2000−x meters
Cost: Cland(x)=240(2000−x) dollars.
Combined Objective Function:
C(x)=400360,000+x2+240(2000−x)
Step 2: Establish the Context-Driven Physical Domain
The downstream crossing point P(x,0) must physically lie between the direct perpendicular alignment (x=0) and the terminal outfall location (x=2000):
Domain: x∈[0,2000] meters
Because the domain is a closed bounded interval [a,b], the Extreme Value Theorem guarantees the existence of an absolute minimum, which can be identified using the Closed Interval Method.
Because 450∈[0,2000], x=450 m is a valid physical critical number.
Step 4: Deconstructing Snell's Law Equivalence
Notice the structure of the critical point condition:
6002+x2x=400240=0.6
Let θ represent the angle between the diagonal wetland pipeline and the perpendicular bank normal. Then sinθ=6002+x2x=53. The ratio of unit construction costs directly mirrors Snell's Law in optics:
Optimal Route: The effluent pipeline should cross the wetland along a 750-meter diagonal path reaching the southern riverbank exactly 450 meters downstream, then follow the dry utility easement for the remaining 1,550 meters to outfall terminal T.
Capital Cost Savings: This mathematically optimized trajectory yields an absolute minimum capital cost of $672,000, generating:
$48,000 in savings (6.7%) compared to a naive perpendicular crossing ($720,000).
$163,224 in savings (19.5%) compared to a direct diagonal line ($835,224).